Question: Verify the schedulability under earliest deadline first algorithm and construct the schedule of the following task set: 1 {1, 5, 4}, 2
Verify the schedulability under earliest deadline first algorithm and construct the schedule of the following task set: τ1 ≡ {1, 5, 4}, τ2 ≡ {2, 8, 6}, and τ3 ≡ {1, 4, 3}. Here, the notation τi ≡ {ei , pi , Di} gives the execution time, ei , period, pi , and relative deadline, Di , of task τi .