Question: 18. Using graphical method, find the minimum elapsed time to perform jobs J1 and J2 on machines A through D, the sequence and process timing
18. Using graphical method, find the minimum elapsed time to perform jobs J1 and J2 on machines A through D, the sequence and process timing for which are given as follows:
Job 1 Sequence Time (Hrs): Job 2 Sequence Time (Hrs): 42 A B 4 B C 6 5 7552 C D 1 D A 3