Question: 18. Using graphical method, find the minimum elapsed time to perform jobs J1 and J2 on machines A through D, the sequence and process timing

18. Using graphical method, find the minimum elapsed time to perform jobs J1 and J2 on machines A through D, the sequence and process timing for which are given as follows:Job 1 Sequence Time (Hrs): Job 2 Sequence Time (Hrs): 42 A

Job 1 Sequence Time (Hrs): Job 2 Sequence Time (Hrs): 42 A B 4 B C 6 5 7552 C D 1 D A 3

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Understanding Management Questions!