Question: Using graphical method, determine the minimum time needed to process the two jobs on six machines. The information about the machine sequence and the time
Using graphical method, determine the minimum time needed to process the two jobs on six machines. The information about the machine sequence and the time required by each job on each machine is given here.


Job 1 Job 2 Time Machine Time Sequence (Hours) Machine Sequence (Hours) A 4 B 6 BCDE F 32435 ACFDE 51365