Question: Suppose production requirements in Solved Problem 9.2 increase and require a reduction in cycle time from 8 minutes to 7 minutes. Balance the line once
Suppose production requirements in Solved Problem 9.2 increase and require a reduction in cycle time from 8 minutes to 7 minutes. Balance the line once again, using the new cycle time. Note that it is not possible to combine task times so as to group tasks into the minimum number of workstations. This condition occurs in actual balancing problems fairly often.
Step by Step Solution
3.47 Rating (170 Votes )
There are 3 Steps involved in it
Performance Time Task Must Follow Task in minutes Th... View full answer