Question: Suppose the information in Problem 2 was supplemented by importance weights for each of the four assessment criteria, where 1 = low importance and 4
.png)
Assume, too, that evaluations of high receive a score of 3, medium 2, and low 1. Recreate your project scoring model and reassess the four project choices (A, B, C, and D). Now which project alternative the best? Why?
Assessment Criteria: 1. Payoff potential 2. Lack of risk 3. Safety 4. Competitive advantage Importance Weights
Step by Step Solution
3.47 Rating (163 Votes )
There are 3 Steps involved in it
Therefore they should choose Project D which has the highest tota... View full answer