Question: Table 8.17 shows the normal time, crash time, and crash costs for the project described in Table 8.16. a. Based on the information provided in
.png)
a. Based on the information provided in Table 8.17, develop a cost and time tradeoff table.
b. If an additional $10,000 can be spent, what will be the new project duration?
Normal Activity Duration Duration Crash Cost (per day) $5,000 $2,000 (days) (days) $1,500
Step by Step Solution
3.36 Rating (162 Votes )
There are 3 Steps involved in it
a To conduct a time and cost tradeoff analysis we need to first identify the critical path and durat... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
792-B-M-L-S-C-M (4579).docx
120 KBs Word File
