Question: Table 8.17 shows the normal time, crash time, and crash costs for the project described in Table 8.16. a. Based on the information provided in

Table 8.17 shows the normal time, crash time, and crash costs for the project described in Table 8.16.
Table 8.17 shows the normal time, crash time, and crash

a. Based on the information provided in Table 8.17, develop a cost and time tradeoff table.
b. If an additional $10,000 can be spent, what will be the new project duration?

Normal Activity Duration Duration Crash Cost (per day) $5,000 $2,000 (days) (days) $1,500

Step by Step Solution

3.36 Rating (162 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

a To conduct a time and cost tradeoff analysis we need to first identify the critical path and durat... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

792-B-M-L-S-C-M (4579).docx

120 KBs Word File

Students Have Also Explored These Related Management Leadership Questions!