Table shows the tasks required to assemble an aluminum storm door and the length of time needed

Question:

Table shows the tasks required to assemble an aluminum storm door and the length of time needed to complete each task.


Table shows the tasks required to assemble an aluminum storm


(a) Calculate the cycle time needed to produce 480 doors in an eight-hour work day.
(b) What is the minimum number of workstations that can be used on the line and still achieve the desired production rate? Balance the line and calculate its efficiency.
(c) What is the maximum output possible with these data? Theminimum?