Question: Table shows the tasks required to assemble an aluminum storm door and the length of time needed to complete each task. (a) Calculate the cycle
Table shows the tasks required to assemble an aluminum storm door and the length of time needed to complete each task.
.png)
(a) Calculate the cycle time needed to produce 480 doors in an eight-hour work day.
(b) What is the minimum number of workstations that can be used on the line and still achieve the desired production rate? Balance the line and calculate its efficiency.
(c) What is the maximum output possible with these data? Theminimum?
Table Task Information for Problem 19 Task Time (sec) 32 43 12 23 15 25 20 Task Immediate Predecessor None B, C,D None E G
Step by Step Solution
3.37 Rating (163 Votes )
There are 3 Steps involved in it
a Assuming the design is to produce 480 doors in an 8hour work day 480 doors 8 hours 60 doorsho... View full answer