Question: The activities described by the following table are given for the Duplaga Corporation: (a) Draw the appropriate AON PERT diagram for Ed Duplagas management team.
.png)
(a) Draw the appropriate AON PERT diagram for Ed Duplagas management team.
(b) Find the critical path.
(c) What is the project completiontime?
Immediate Predecessor(s) Activity Time E, F G, H
Step by Step Solution
3.38 Rating (164 Votes )
There are 3 Steps involved in it
a b c Task Time ES EF LS LF Slack A 9 0 9 0 9 0 B 7 9 1... View full answer