Question: The activities described by the following table are given for the Howard Corporation in Kansas: a) Draw the appropriate AON PERT diagram for J. C.
The activities described by the following table are given for the Howard Corporation in Kansas:
.png)
.png)
a) Draw the appropriate AON PERT diagram for J. C. Howards management team.
b) Find the critical path.
c) What is the project completiontime?
Immediate Activity Predecessor s Time 4 E.F G.H
Step by Step Solution
★★★★★
3.39 Rating (171 Votes )
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
a b c Task Time ES EF LS LF Slack A 9 0 9 0 9 0 B 7 9 1... View full answer