Question: The BOM for product A is given below: Assume the master schedule calls for 200 units of product A in week 5 and 250 units
.png)
Assume the master schedule calls for 200 units of product A in week 5 and 250 units in week 6.
a. Develop a materials plan for this product.
b. What actions should be taken immediately?
c. Project the inventory ahead for each part.
d. If you were suddenly notified that part D will take three weeks to get instead of two weeks, what actions would you take?
Part On Hand Weeks of Lead Time 75 150 50 100 C(2) D(2)
Step by Step Solution
3.33 Rating (168 Votes )
There are 3 Steps involved in it
a NAME SECT DATE 18Dec02 MATERIALS PLAN FOR PRODUCT A PART 1 2 3 4 5 6 A GROSS REQUIREMENTS 0 0 0 0 ... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
555-B-M-L-S-C-M (3673).docx
120 KBs Word File