Question: The Daugherty Porta-Vac project discussed in Section 13.2 has an expected project completion time of 17 weeks. The probability that the project could be completed
A-D-G-J
A-C-F-J
B-H-I-J
a. Use the information in Table to compute the expected time and variance for each path shown.
b. Compute the probability that each path will be completed in the desired 20-week period.
c. Why is the computation of the probability of completing a project on time based on the analysis of the critical path? In what case, if any, would making the probability computation for a noncritical path be desirable?
TABLE
EXPECTED TIMES AND VARIANCES FOR THE PORTA-VAC
PROJECTACTIVITIES
.png)
931 7411 7 1 0 2 6 0 1 1001000000 4 1813 el 62353234222 tiv ABCDEFGHIJ
Step by Step Solution
3.41 Rating (167 Votes )
There are 3 Steps involved in it
a ADGJ ET 6 5 3 2 16 2 178 178 025 011 392 ACFJ ET 6 3 2 2 13 2 178 011 003 011 203 BHIJ ET 2 ... View full answer