Question: The float associated with each project task can only be derived following the completion of the forward and backward passes. Explain why this is true.
Step by Step Solution
3.49 Rating (162 Votes )
There are 3 Steps involved in it
The forward pass establishes the earliest time that activities in the network c... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
663-B-M-L-P-M (2127).docx
120 KBs Word File
