Question: The following activities were observed for a mold operator: a) operator removes molded piece from die, b) walks to bench, puts the piece into box
The following activities were observed for a mold operator:
a) operator removes molded piece from die,
b) walks to bench, puts the piece into box and the puts the box on a pallet,
c) returns to injection molder,
d) blows out dirt from die (with compressed air) ,
e) sprays oil into die,
f) presses START button on molder and sits down,
g) the machines closes die, injects plastic into die, after set curing time of 2 min opens die,
h) cycle repeats itself
Complete a flow process chart for the mold operator. What is one major problem in the job and how can it be improved?
Step by Step Solution
3.48 Rating (158 Votes )
There are 3 Steps involved in it
Based on the following flow process chart there are two unnecessary excess travel distances ... View full answer
Get step-by-step solutions from verified subject matter experts