Question: The following information is known about a project a. Draw the network diagram for this project. b. Determine the critical path and project duration c.
.png)
a. Draw the network diagram for this project.
b. Determine the critical path and project duration
c. Calculate the slack for eachactivity
Activity Activity Time (day s) Immediate Predecessors) ,
Step by Step Solution
3.44 Rating (170 Votes )
There are 3 Steps involved in it
a AON diagram b The critical path is ACDEG with a completion time of 24 days Earlies... View full answer