Question: The following information is known about a project a. Draw the network diagram for this project. b. Determine the critical path and project duration c.

The following information is known about a project

The following information is known about a project  .:.

a. Draw the network diagram for this project.
b. Determine the critical path and project duration
c. Calculate the slack for eachactivity

Activity Activity Time (day s) Immediate Predecessors) ,

Step by Step Solution

3.44 Rating (170 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

a AON diagram b The critical path is ACDEG with a completion time of 24 days Earlies... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock