Question: Consider the following data for a project; a. Draw the network diagram. b. Calculate the critical path for this project. c. How much slake is

Consider the following data for a project;

Consider the following data for a project;  .:. a.

a. Draw the network diagram.
b. Calculate the critical path for this project.
c. How much slake is in activities G, H, andI.

ActivityActivity Time (days) Immediate Predecessors) B,C D,E G, HI

Step by Step Solution

3.22 Rating (169 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

a AON network diagram b The critical path is ACFHJ with a completion time of 27 days c Earli... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)