Question: Consider the following data for a project; a. Draw the network diagram. b. Calculate the critical path for this project. c. How much slake is
.png)
a. Draw the network diagram.
b. Calculate the critical path for this project.
c. How much slake is in activities G, H, andI.
ActivityActivity Time (days) Immediate Predecessors) B,C D,E G, HI
Step by Step Solution
3.22 Rating (169 Votes )
There are 3 Steps involved in it
a AON network diagram b The critical path is ACFHJ with a completion time of 27 days c Earli... View full answer