Question: The following information relates to a project (task times are in weeks): What is the projects completion time for which we are 95 percent sure

The following information relates to a project (task times are in weeks):
The following information relates to a project (task times are

What is the project€™s completion time for which we are 95 percent sure of success?

Task Preceding Tasks to None None 10 12 14 12 14 10 19 16 18 15 C, D 10

Step by Step Solution

3.42 Rating (161 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Before we can calculate the completion time that would provide a 95 percent chance of success w... View full answer