Question: The following precedence network displays the 3-Point estimates for each activity of a project. Determine: a. The expected duration for each path and its variance.

The following precedence network displays the 3-Point estimates for each activity of a project. Determine:
a. The expected duration for each path and its variance.
b. The probability that the project will require more than 49 weeks.
c. The probability that the project can be completed in 46 weeks or less.

The following precedence network displays the 3-Point estimates for each

11-12-13 2 9-10-12 3 5-7-10 4 14-18-26 8-10-14 5-6-7 5 End 8-8-8 13-13-13 10.5-13-15.5 13 10-1214 7-10 12 10-11-12 10 12

Step by Step Solution

3.34 Rating (157 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

a 1234 1567 1589 Path b 43 40 110111213 4683 C Mean 3734 Activity 1 2 in 5 10 3 ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

686-B-M-L-O-M (5300).docx

120 KBs Word File

Students Have Also Explored These Related Management Leadership Questions!