Question: The R&D department is planning to bid on a large project for the development of a new communications system for commercial planes. The accompanying table
The R&D department is planning to bid on a large project for the development of a new communications system for commercial planes. The accompanying table shows the activities, times, and sequences required:
.png)
a. Draw the network diagram.
b. What is the critical path?
c. Suppose you want to shorten the completion time as much as possible, and you have the option of shortening any or all of B, C, D, and G each one week. Which would you shorten?
d. What is the new critical path and earliest completiontime?
324466233 DF G, ABCDEFGHI
Step by Step Solution
3.50 Rating (170 Votes )
There are 3 Steps involved in it
a b ACFGI and ADFGI at 18 weeks c B is not on a cri... View full answer