Question: The following table shows orders to be processed at a machine shop as of 8: 00 a. m. Monday. The jobs have different operations they
a. Determine the processing sequence at the first work center using each of these rules:
(1) FCFS,
(2) S/ O.
b. Compute the effectiveness of each rule using each of these measures:
(1) Average flow time,
(2) Average number of jobs at the workcenter.
.png)
Remaining Date Number of Job(days)(days) Operations Processing Due Time 20 18 25 17 35 10