Question: The manager at Ormonde, Inc. collected the value stream mapping data from the plants most problematic manufacturing cell that fabricates parts for washing machines. This
.png)
a. What is the cells current inventory level?
b. What is the takt time for this manufacturing cell?
c. What is the production lead time at each process in the manufacturing cell?
d. What is the total processing time of this manufacturing cell?
e. What is the capacity of this manufacturingcell?
Average demand: 550/day Batch size: 20 Number of shifts per day: 3 Availability: 8 hours per shift with a 45-minute lunch break Cutting Overall Process Attributes Process Step 1 Cycle time 120 seconds Setup time 3 minutes Up time-100% Operators = 1 WIP-400 units (Before Cutting) Cycle time -250 seconds Setup time 5 minutes Up time-99% Operators 2 WIP 500 units (Before Bending) Cycle time 140 seconds Setup time none Up time-100% Operators 1 WIP 200 units (Before Punching) WP = 1,000 units (After Punching) Process Step 2 Bending Process Step 3 Punching Customer Shipments One shipment of 2,750 units each week All communications with customer are electronic There is a weekly order release to Cutting All material is pushed Information Flow
Step by Step Solution
3.50 Rating (167 Votes )
There are 3 Steps involved in it
Ormonde Inc a The cells current inventory level is 4005002001000 2100 units b The cells t... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
265-B-M-L-S-C-M (1180).docx
120 KBs Word File