Question: 14. The manager at Ormonde, Inc. collected the value stream mapping data from the plant's most problematic manufacturing cell that fabricates parts for washing machines.



14. The manager at Ormonde, Inc. collected the value stream mapping data from the plant's most problematic manufacturing cell that fabricates parts for washing machines. This data are shown in Table 6.5. Using this data, calculate the current state performance of the cell and answer the following questions. e. What is the capacity of this manufacturing cell? TABLE 6.5 OPERATIONS DATA FOR ORMONDE, INC. Average demand: 550/dwy Batch sire: 20 Number of shifts per day: 3