The operations manager of a large plant wishes to overhaul a machine. After conducting a PERT/CPM analysis

Question:

The operations manager of a large plant wishes to overhaul a machine. After conducting a PERT/CPM analysis he has developed the following critical path.

1. Disassemble machine

2. Determine parts that need replacing

3. Find needed parts in inventory

4. Reassemble machine

5. Test machine

He has estimated the mean (in minutes) and variances of the completion times as follows.


The operations manager of a large plant wishes to overhaul


Determine the mean and variance of the completion time of theproject.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Question Posted: