Question: There are four activities along the critical path for a project. The expected values and variances of the completion times of the activities are listed
There are four activities along the critical path for a project. The expected values and variances of the completion times of the activities are listed here. Determine the expected value and variance of the completion time of theproject.
.png)
Expected Completion Time (Days) 18 12 27 8 Activity Variance 8 5 4 2
Step by Step Solution
3.46 Rating (166 Votes )
There are 3 Steps involved in it
18 12... View full answer