Question: The optical disk project team has started gathering the information necessary to develop the project networkpredecessor activities and activity times in weeks. The results of
.png)
The project team has requested that you create a network for the project, and determine if the project can be completed in 45weeks.
Duration Predecessor Activity Description None Define scope Define customer problems Define data records and relationships Mass storage requirements Consultant needs analysis Prepare installation network Estimate costs and budget Design section "point" system Write request proposal Compile vendor list Prepare mgmt. control system Prepare comparison report Compare system "philosophies" Compare total installation Compare cost of support Compare customer satisfaction level Assign philosophies points Assign installation cost Assign support cost Assign customer satisfaction points Select best system Order system 2,3 2,3 4, 5 4, 5 4, 5 4, 5 10 10 9, 10 8, 12 8, 12 8, 12 8, 12 13 14 15 16 11,17, 18, 19, 20 21 12 13 14 10 17 20 21
Step by Step Solution
3.48 Rating (168 Votes )
There are 3 Steps involved in it
Next is the MS Project Entry Table for the Optical Disk Preinstallation project The estimated comple... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
177-B-M-L-P-M (1357).docx
120 KBs Word File