Question: The professor from problem 6 is considering reducing the time for completion of the project. He can hire a teaching assistant (TA) to help with
a. Which activity should the TA perform to reduce the project completion time by one day?
b. Which activities should the TA perform to re duce the project completion time by two days?
c. Can the network be crashed by three days in total? Explain why or why not?
Step by Step Solution
3.46 Rating (169 Votes )
There are 3 Steps involved in it
a The TA should perform activity D to reduce the project completion time by on... View full answer