Question: The service manager for a bicycle sales and service shop wants to study the length of time required to replace the gears on road bikes.
-1.png)
-2.png)
Use Excel to develop an R chart to determine if the range of the process is stable or not.
Day Bike BikeBikeBike 16.26 22.95 26.12 10.92 33.97 18.8020.6720.04 17.74 28.60 9.96 10.98 27.22 22.02 25.3221.93 30.67 14.65 18.2921.70 20.44 9.48 32.8717.69 19.88 16.961.7927.61 18.1322.06 21.2220.33 21.82 32.2516.5020.11 1025.18 23.24 19.97 17.83 1118.49 13.66 27.44 20.87 12 23.22 17.36 22.25 24.19 13 23.97 21.79 23.14 35.88 14 18.53 25.38 13.31 29.83 15 20.66 26.50 20.42 18.76 16 2132 28.41 29.75 19.91 17 22.92 18.58 18.16 15.60 18 20.5 20.85 23.50 22.74 19 22.15 21.73 21.28 24.94 20 20.17 19.15 22.87 25.89
Step by Step Solution
3.44 Rating (167 Votes )
There are 3 Steps involved in it
Day Bike 1 Bike 2 Bike 3 Bike 4 x Max Min R 1 1626 2295 2612 1092 1906 2612 1092 152 2 3397 188 2067 ... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
629-B-M-L-S-C-M (4282).docx
120 KBs Word File