Question: The table below shows estimates of the optimistic, most probable, and pessimistic times for the situation described in Problem 10. What is the probability the
The table below shows estimates of the optimistic, most probable, and pessimistic times for the situation described in Problem 10. What is the probability the project will be completed in time for Kozar to begin marketing the new product within 27 months?

Immediate Optimistic Most Probable Pessimistic Activity Predecessors Time Time Time A 1. 1.5 B. A C A 3. D . 3.5 6.5 B 12 C, D, E 6.5 7.5 11.5 E 5 6. 13 425 579
Step by Step Solution
3.23 Rating (178 Votes )
There are 3 Steps involved in it
Most Activity Immediate Predecessors Optimistic Time Probable Time Pessimistic Ti... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
546-B-M-L-O-M (4389).docx
120 KBs Word File