Question: The three-station work cell at Pullman Mfg., Inc. is illustrated in figure S7.8. It has two machines at station 1 in parallel (i.e., the product
(a) What is the process cycle time of this work cell?
(b) What is the system process time of this work cell?
(c) If the firm operates 8 hours per day, 6 days per week, what is the weekly capacity of this workcell?
.png)
Station 1 Machine A 20 min/unit .. Yal Station 2 |....-mol Station 3 Station 1 Machine B 20 min/unit 12 min/unit 8 min/unit
Step by Step Solution
3.22 Rating (160 Votes )
There are 3 Steps involved in it
The threestation work cell at Pullman Mfg Converting each capacity to a process time Station ... View full answer