Question: The three-station work cell at Pullman Mfg., Inc. is illustrated in figure S7.8. It has two machines at station 1 in parallel (i.e., the product

The three-station work cell at Pullman Mfg., Inc. is illustrated in figure S7.8. It has two machines at station 1 in parallel (i.e., the product needs to go through only one of the two machines before proceeding to station 2).
(a) What is the process cycle time of this work cell?
(b) What is the system process time of this work cell?
(c) If the firm operates 8 hours per day, 6 days per week, what is the weekly capacity of this workcell?
The three-station work cell at Pullman Mfg., Inc. is illustrated

Station 1 Machine A 20 min/unit .. Yal Station 2 |....-mol Station 3 Station 1 Machine B 20 min/unit 12 min/unit 8 min/unit

Step by Step Solution

3.22 Rating (160 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

The threestation work cell at Pullman Mfg Converting each capacity to a process time Station ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

256-B-M-L-O-M (1634).docx

120 KBs Word File

Students Have Also Explored These Related Management Leadership Questions!