Question: Using the information below, draw an AOA network. Find the critical path and use it to compute the number of days you would be 95

Using the information below, draw an AOA network. Find the critical path and use it to compute the number of days you would be 95 percent sure the project would be completed. Calculate the slack, earliest start, and latest start times for each activity and show in table form. Does any path come close to causing a problem in determining the probability of project completion based on the critical path alone?
Using the information below, draw an AOA network. Find the

b 10 7 6 0 1 1 1 1 2 0 1 4 5 4 5 9 110111159 m3660 11 14 8 9 10 0 15 12 12 4 5 a-656 5780 14 10 9 057 9780011

Step by Step Solution

3.34 Rating (175 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

The critical path in the above diagram is 14 45 56 67 710 1011 with a duration of 59 days Tabulating ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

84-B-M-L-P-M (465).docx

120 KBs Word File

Students Have Also Explored These Related Management Leadership Questions!