Question: Using the process load in the previous problem, suppose a system uses SJN scheduling a. Create a Gantt chart illustrating the execution of these processes.
Using the process load in the previous problem, suppose a system uses SJN scheduling
a. Create a Gantt chart illustrating the execution of these processes.
b. What is the turnaround time for process p4?
c. What is the average wait time for the processes?