Question: What is the variance in completion time for the critical path found in Problem 2? In problem 2 Activity Variance 1/9 1/9 12 A/ i/S

What is the variance in completion time for the critical path found in Problem 2?
In problem 2
What is the variance in completion time for the critical
What is the variance in completion time for the critical

Activity Variance 1/9 1/9 12 A/ i/S Activity C Activity A Activity E t- Activity D t-3 Activity B t-2