Question: Wild Widget must set up an assembly line for widgets. Forecasts show that 50 units per hour should be produced. The tasks required, task times,

Wild Widget must set up an assembly line for widgets. Forecasts show that 50 units per hour should be produced. The tasks required, task times, and precedence relationships are as follows:

Wild Widget must set up an assembly line for widgets.

a. Draw the precedence diagram.
b. What is the takt time?
c. What is the theoretical number of workstations
d. Assign the tasks to the workstations to balance the line using the longest operating time rule.
e. What is the efficiency of the balanced line?
f. If demand decreased to 40 units per day, what changes would be needed, if any?

Task Time (seconds) Predecessors 10 30 15 35 25 10 35 C, B E. F

Step by Step Solution

3.34 Rating (178 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

a b Takt time 60 minhour x 60 secmin50 unitshour 72 seconds per u... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

434-B-M-L-S-C-M (2291).docx

120 KBs Word File

Students Have Also Explored These Related Management Leadership Questions!