Williams Optical Inc. is considering a new lean product cell. The present manufacturing approach produces a product

Question:

Williams Optical Inc. is considering a new lean product cell. The present manufacturing approach produces a product in four separate steps. The production batch sizes are 45 units. The process time for each step is as follows:

Process Step................15 minutes

Process Step................28 minutes

Process Step................34 minutes

Process Step................43 minutes

The time required to move each batch between steps is 5 minutes. In addition, the time to move raw materials to Process Step 1 is also 5 minutes, and the time to move completed units from Process Step 4 to finished goods inventory is 5 minutes.

The new lean layout will allow the company to reduce the batch sizes from 45 units to 3 units. The time required to move each batch between steps and the inventory locations will be reduced to 2 minutes. The processing time in each step will stay the same.

Determine the value-added, non-value-added, and total lead times, and the value-added ratio under the (a) present and (b) proposed production approaches. Round percentages to one decimal place.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  answer-question

Managerial Accounting

ISBN: 978-1285866307

13th edition

Authors: Carl S. Warren, James M. Reeve, Jonathan Duchac

Question Posted: