Question: You are creating a database for the Oklahoma City Thunder NBA Basketball team.Given the project network that follows, complete the forward and backward pass, compute

You are creating a database for the Oklahoma City Thunder NBA Basketball team.Given the project network that follows, complete the forward and backward pass, compute activity slack, and identify the critical path.Use this information to create a Gantt chart for the project.

9E 15 Develop Input Screens 6 20 14 5 þesign 1/O 10 4 14 F 13 Develop utput Reports A 20 H 22 4 20 16 22 | 25 Problem S

9E 15 Develop Input Screens 6 20 14 5 esign 1/O 10 4 14 F 13 Develop utput Reports A 20 H 22 4 20 16 22 | 25 Problem System Analysis Test Implement System Definition System 20 2 22 22| 3 25 5 D 15 15 G 20 Design Database Create Database 5 10 15 15 5 20 Legend ES ID EF SL Description LS DUR LF

Step by Step Solution

3.32 Rating (161 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Early start late start early finish late finish and slack are show... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

1379-B-M-L-P-M(2674).docx

120 KBs Word File

Students Have Also Explored These Related Management Leadership Questions!