Question: You are creating a database for the Oklahoma City Thunder NBA Basketball team.Given the project network that follows, complete the forward and backward pass, compute
You are creating a database for the Oklahoma City Thunder NBA Basketball team.Given the project network that follows, complete the forward and backward pass, compute activity slack, and identify the critical path.Use this information to create a Gantt chart for the project.
.png)
9E 15 Develop Input Screens 6 20 14 5 esign 1/O 10 4 14 F 13 Develop utput Reports A 20 H 22 4 20 16 22 | 25 Problem System Analysis Test Implement System Definition System 20 2 22 22| 3 25 5 D 15 15 G 20 Design Database Create Database 5 10 15 15 5 20 Legend ES ID EF SL Description LS DUR LF
Step by Step Solution
3.32 Rating (161 Votes )
There are 3 Steps involved in it
Early start late start early finish late finish and slack are show... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
1379-B-M-L-P-M(2674).docx
120 KBs Word File