Question: You are given the following information about a project consisting of six activities: (a) Construct the project network for this project. (b) Find the earliest
.png)
(a) Construct the project network for this project.
(b) Find the earliest times, latest times, and slack for each activity. Which of the paths is a critical path?
(c) If all other activities take the estimated amount of time, what is the maximum duration of activity D without delaying the completion of the project?
Inmediate Predecessors Estiinated Duration Activity 5 months 1 month 2 months 4 months 6 months 3 months A, C D, E
Step by Step Solution
3.41 Rating (164 Votes )
There are 3 Steps involved in it
a b Critical Pat... View full answer