You are presented with the following information for Duncan Limited:

Budgeted production: 1000 units.

Actual production: 1200 units.

Standard specification for one unit: 10 hours at £8 per direct labour hour.

Actual direct labour cost: £97,200 in 10,800 actual hours.


Required:

Calculate the following variances:

(a) Direct labour total

(b) Direct labour rate

(c) Direct labour efficiency.