You are product planner for product A (in problem 14.14 and figure 14.16). the field service manager,

Question:

You are product planner for product A (in problem 14.14 and figure 14.16). the field service manager, Al Trostel, has just called and told you that the requirements for B and F should each be increased by 10 units for his repair equipments in the field.

You are product planner for product A (in problem 14.14

(a) Prepare a list showing the quantity of each part required to produce the requirements for the service manager and the production request of 10 Bs and Fs.
(b) Prepare a net requirement plan by date for the new requirements (for both production and field service), assuming that the field service manager wants his 10 units of B and F in week 6 and the 10 production units of A in week8.