Question: You are the project manager of the software installation project in Table. You like to find the minimum cost schedule for your project. There is
You are the project manager of the software installation project in Table. You like to find the minimum cost schedule for your project. There is a $1,000 per week penalty for each week the project is delayed beyond week 25. In addition, your project team determined that indirect project costs are $2,500 per week.
.png)
a. What would be your target completion week?
b. How much would you save in total projects costs with yourschedule?
DATA FOR SOFTWARE INSTALLATION PROJECT ActivityImmediate Predecessors Normal Time (weks) Normal Cost (S)Crash Time (weeks) Crash Cost (S) 2,000 5,000 10,000 3,000 4.000 8.000 2,000 6,000 7,000 4,000 8,000 12,000 7.000 5,000 14,000 2,000 9,000 16,000 10 A,B 2 E. F C, F
Step by Step Solution
3.47 Rating (173 Votes )
There are 3 Steps involved in it
The AON diagram for the software installation project is below The crashing data are given in the fo... View full answer