Question: Consider the project described in Table. a. if you start the project immediately. When will it be finished? b. You are interested in completing your
.png)
a. if you start the project immediately. When will it be finished?
b. You are interested in completing your project as soon as possible. You have only one option. Suppose you could assign Employee A, currently assigned to Activity G, to help Employee B, currently assigned to activity E each week that Employee A helps B will result in Activity G increasing its time by one week and Activity F reducing its time by one week. How many weeks should Employee A works on ActivityF?
PROJECT DATA FOR PROBLEM 26 Activity START Activity Time (weeks) Immediate Predecessorts) START START A B D, E FINISH F G
Step by Step Solution
3.58 Rating (169 Votes )
There are 3 Steps involved in it
The AON diagram for the project is below Additional data for the project are co... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
227-B-M-L-O-M (923).docx
120 KBs Word File