Question: You have signed a contract to build a garage for the Simpsons. You will receive a $500 bonus for completing the project within 7 working
You have signed a contract to build a garage for the Simpsons. You will receive a $500 bonus for completing the project within 7 working days. The contract also contains a penalty clause in which you will lose $100 for each day the project takes longer than 7 working days.
Draw a project network given the information below. Complete the forward and backward pass, compute the activity slack, and identify the critical path. Do you expect to receive a bonus or a penalty on this project?
.png)
ID Description Time (days) Predecessor Prepare site A None 2 Pour foundation B B 3 Erect frame 4 Roof D 4 Windows 1 Doors 1 Electrical G D,E,F,G 3 Rough-in frame F,G .I Door opener Paint Cleanup K 1
Step by Step Solution
3.37 Rating (166 Votes )
There are 3 Steps involved in it
Early start late start early finish late finish and slack are shown on the diagram above The compl... View full answer