Question: Consider the following project activities: a. Draw the project network diagram. b. Identify all the paths through the network and their lengths. c. Identify all
Consider the following project activities:
a. Draw the project network diagram.
b. Identify all the paths through the network and their lengths.
c. Identify all the critical activities and path(s). How long will the entire project take?
DURATION ACTIVITY (DAYS) PREDECESSORS A 3 None B 2 None A , C, D D 1.5 E 2.5 F 3.5 G 4 E, F