Question: Consider the following project activities: a. Draw the project network diagram. b. Identify all the paths through the network and their lengths. c. Identify all
Consider the following project activities:
a. Draw the project network diagram.
b. Identify all the paths through the network and their lengths.
c. Identify all the critical activities and path(s). How long will the entire project take?
d. After you complete part b and before you perform the forward and backward passes, you should already be able to tell that activities A and N are on the critical path(s). Why?
DURATION ACTIVITY (DAYS) PREDECESSORS A 4 None B 3 7 9 A E 8 A F 7 B G 6 H. 13 4 D, E J 12 E 1 E F, G, H I, J, K L, M M 4 AA
Step by Step Solution
3.57 Rating (154 Votes )
There are 3 Steps involved in it
tr msoheightsourceauto col msowidthsourceauto br msodataplacementsamecell style0 msonumberformatGeneral textaligngeneral verticalalignbottom whitespacenowrap msorotate0 msobackgroundsourceauto msopatt... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
436-B-M-L-S-C-M (2841).xlsx
300 KBs Excel File