Question: A construction project is broken down into the following 10 activities: a. Draw the network diagram. b. Find the critical path. c. If activities 1
.png)
a. Draw the network diagram.
b. Find the critical path.
c. If activities 1 and 10 cannot be shortened, but activities 2 and 9 can be shortened to a minimum of one week each at a cost of $10,000 per week, which activities would you shorten to cut the project by fourweeks?
ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) 2,3 6,7 8, 9 10
Step by Step Solution
3.38 Rating (173 Votes )
There are 3 Steps involved in it
a b 136910 length 26 weeks c The most logical option w... View full answer