Question: Suppose that a supplier ships components in lots of size 5,000. A single-sampling plan with and is being used for receiving inspection. Rejected lots are

Suppose that a supplier ships components in lots of size 5,000. A single-sampling plan with 50 and  is being used for receiving inspection. Rejected lots are screened, and all defective items are reworked and returned to the lot. 

a. Draw the OC curve for this plan.

b. Find the level of lot quality that will be rejected 90% of the time.

c. Management has objected to the use of the above sampling procedure and wants to use a plan with an acceptance number , arguing that this is more consistent with their Zero Defects program. What do you think of this?

d. Design a single-sampling plan with  that will give a 0.90 probability of rejection of lots having the quality level found in part (b). Note that the two plans are now matched at the LTPD point. Draw the  curve for this plan and compare it to the one for in part (a).

e. Suppose that incoming lots are 0.5% nonconforming. What is the probability of rejecting these lots under both plans? Calculate the ATI at this point for both plans. Which plan do you prefer? Why?

50

Step by Step Solution

3.42 Rating (161 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

a Excel formulas Excel results Excel graph b If then From the graph in part a wit... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

552-M-S-Q-C-B-S (393).docx

120 KBs Word File

Students Have Also Explored These Related Statistics Questions!