Question: A foreman has determined the expected processing times at a machine for a set of jobs and now wants to sequence them. Given the following

A foreman has determined the expected processing times at a machine for a set of jobs and now wants to sequence them. Given the following information, do the following:
Job Job Time (days) Due Date (days)
a 4.510
b 6.017
c 5.212
d 1.627
e 2.818
f 3.319
a-1. Determine the processing sequence using (1) MST,(2) SPT,(3) EDD, and (4) CR.
Rule Sequence
MST
(Click to select)
SPT
(Click to select)
EDD
(Click to select)
CR
(Click to select)
a-2. For each sequence, calculate the average days late, the average flow time, and the average WIP. (Do not round intermediate calculations. Round the final answers to 2 decimal places.)
Rule Average lateness Average flow time Average WIP
MST & EDD
day(s)
day(s)
jobs
SPT
day(s)
day(s)
jobs
CR
day(s)
day(s)
jobs
b. Which rule is best?
(Click to select)
has the lowest average flow time & average WIP, but
(Click to select)
have the lowest average days late.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!