Question: A PLC is used to control the sequence in an automatic drilling operation. A human operator loads and clamps a raw work part into a
(a) Specify the input/output variables for this system operation and define symbols for them (e.g., X1, X2, C1, Y1, etc.).
(b) Construct the ladder logic diagram for the system.
(c) Write the low level language statements for the system.
Step by Step Solution
3.39 Rating (158 Votes )
There are 3 Steps involved in it
a Let X1 spindle up X2 spindle at desired depth X3 fixture at position 1 X... View full answer