Question: a. Refer to the table below. What is the cumulative budgeted cost at the end of week 6? Amounts are in thousands of dollars. b.
a. Refer to the table below. What is the cumulative budgeted cost at the end of week 6?

Amounts are in thousands of dollars.
b. Below is a table of actual costs. What is the cumulative actual cost at the end of week 6? Determine whether there is a cost overrun or under run. What is causing it?

Amounts are in thousands of dollars.
c. Below is a table of the cumulative percentages of work completed by the end of week 6. What is the cumulative earned value of the project at the end of week 6? Is it good?

Amounts are cumulative percentages complete.
d. What is the CPI at the end of week 6? What is the CV?
e. Calculate the FCAC using the first two methods described in the chapter. In addition, describe a third FCAC method you could use.
Week TBC 3. 4 9. 10 Task 1 30 10 15 20 10 10 Task 2 10 10 70 Task 3 40 25 Task 4 20 30 Total 170 10 25 15 10 25 15 35 10 20 Cumulative LO
Step by Step Solution
3.40 Rating (175 Votes )
There are 3 Steps involved in it
a The cumulative budgeted cost at the end of week 6 is 100000 b Week 1 2 3 4 5 6 Cumulative 10 36 54 ... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
192-B-M-L-P (233).docx
120 KBs Word File
