Question: Electro Fans has just received an order for one thousand 20-inch fans due week 7. Each fan consists of a housing assembly, two grills, a
.png)
(a) Construct a product structure.
(b) Construct a time-phased product structure.
(c) Prepare a net material requirementsplan.
Lead On Hand' Lot Scheduled ComponentTime Inventory Size Receipt 20 Fan 100 100 kHousing Frame 2 Supports (2)I Handle 50 100 400 500 200 500 150 Grills (2) Fan Asscmbly 3 2 Hub Blades (5 2 100 Electrical Unit1 Motor Switch Knob 20 12 25 200 knobs in week 2
Step by Step Solution
3.26 Rating (167 Votes )
There are 3 Steps involved in it
To tackle this problem we need to go through each part constructing a product structure a timephased structure and then preparing a net material requi... View full answer