Question: Based on the precedence table below, draw a network diagram for this project. Identify the critical path, earliest start and finish, and slack for each
Based on the precedence table below, draw a network diagram for this project. Identify the critical path, earliest start and finish, and slack for each task.
The critical path tasks are C,F, I, K, and L.
.png)
Activity Duration Immediate Days Predecessor none none none D, E G.J.K
Step by Step Solution
3.27 Rating (176 Votes )
There are 3 Steps involved in it
Task Immediate Predecessors Earliest Start ES Earliest Completio... View full answer