Question: Consider the following information for a project to add a drive-thru window at Crestview Bank. a. Draw the network diagram for this project. b. Specify
Consider the following information for a project to add a drive-thru window at Crestview Bank.
.png)
a. Draw the network diagram for this project.
b. Specify the critical path.
c. Calculate the slack for activities A andD.
Activity Activity Time (weeks) Immediate Predecessor(s) A, B D, C . E, C F, G
Step by Step Solution
3.35 Rating (167 Votes )
There are 3 Steps involved in it
Crestview Bank a The AON diagram is b The critical path is BEGH w... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
265-B-M-L-O-M (2256).docx