Question: Consider the following information for a project to add a drive-thru window at Crestview Bank. a. Draw the network diagram for this project. b. Specify
.png)
a. Draw the network diagram for this project.
b. Specify the critical path.
c. Calculate the slack for activities A andD.
Activity Activity Time (weeks) Immediate Predecessor(s) A, B D, C . E, C F, G
Step by Step Solution
3.35 Rating (167 Votes )
There are 3 Steps involved in it
Crestview Bank a The AON diagram is b The critical path is BEGH w... View full answer